Center for Urban Waters Construction Project
Project Schedule
A project timeline highlighting major milestones is shown below. This timeline is tentative and subject to change as the project moves forward.
|
Schedule |
Activity |
|
March 2007 |
Property purchased |
|
June 2007 |
NDC selected as nonprofit facilitator |
|
July 2007 |
Perkins + Will selected as architect |
|
September 2007 |
Design program completed |
|
October 2007 |
Basis of Design document completed |
|
December 2007 |
City Council approved lease agreement |
|
October 2008 |
Final design & construction documents completed |
|
November 2008 |
Project competitively bid by Lorig |
|
February 2009 |
Bonds to finance construction sold by TES Properties |
|
March 2009 |
Construction began |
|
April 2010 |
Substantial completion of the facility |